Trump Files Suit Against Lenders

Developer Seeks to Extend $640 Million Loan on a Chicago Skyscraper

 

P1130566.JPG

 

Wsj.com

By ALEX FRANGOS

 

Tall Trouble: Donald Trump's Chicago skyscraper project, the Trump International Hotel & Tower, during construction in July.

 

Mr. Trump is suing to extend a $640 million senior construction loan on the 92-story Trump International Hotel & Tower from a group of lenders led by Deutsche Bank AG and including a unit of Merrill Lynch & Co., Union Labor Life Insurance Co., iStar Financial Inc., a publicly traded real-estate investment trust, and Highland Funds, a unit of Highland Capital Management LP.

 

The tower, which contains 339 hotel rooms and 486 condominiums, will be the second-tallest building in the U.S. behind Chicago's Sears Tower and is expected to be completed in mid-2009. The hotel, on the lower floors, opened earlier this year. But sales of both the hotel rooms and the condominiums have come in below original estimates and the project's current projected revenue remains short by nearly $100 million needed to pay off the senior lenders.

 

The lawsuit, filed in New York State supreme court in Queens, is a further indication of the dysfunction in the real-estate lending markets as borrowers and lenders struggle to resolve troubled projects. People familiar with the matter say the lender group, which is made up of more than a dozen institutions, was unable to agree on the extension.

 

The suit demands -- among other things -- that an extension provision in the original loan agreement be triggered because of the "unprecedented financial crisis in the credit markets now prevailing, in part due to acts Deutsche Bank itself participated in." This so-called force majeure provision is common in contracts and can be applied to acts of war and natural disasters. Mr. Trump already extended the loan once in May.

From the Archives

 

Mr. Trump asked for $3 billion in damages. The suit won't affect construction of the project, according to people familiar who say there is enough money to complete the $90 million work that is left.

 

The suit says Mr. Trump attempted to resolve the impasse by offering to buy the project's unsold hotel units for $97 million. That money would be used to pay down the construction loan, along with the $204 million in proceeds from closed units and the $353 million that is expected from units that close in the next six months. A Deutsche Bank spokesman declined to comment.

 

Mr. Trump has put $77 million of his own equity into the tower, which he would stand to lose in a potential foreclosure. Other than a $40 million guarantee to complete the project, Mr. Trump has no recourse obligations to the project. A Trump spokesman declined to comment.

[Trump, Donald]

 

Deutsche Bank originated the construction loan in 2005 and sold off most of it to others, retaining less than $10 million of exposure on that loan. The suit alleges that Deutsche Bank compromised the senior construction loan by selling pieces off to "so many institutions, banks, junk bond firms, and virtually anybody that seemed to come along," that the lending group is unable to come to a consensus on how to deal with the matter.

 

It also alleges Deutsche Bank created a "serious conflict of interest" by taking a separate stake in the project's so-called mezzanine loan that was originated by private-equity firm Fortress Investment Group. The mezzanine loan, which is junior to the senior construction loan, had an original principal of $130 million but will eventually accrue to $360 million. Deutsche Bank purchased roughly one-quarter of the mezzanine loan, according to people familiar with the matter.

 

The suit names the mezzanine lenders as defendants, including Fortress and its affiliates, Newcastle Investment Corp. and Drawbridge Special Opportunities Fund, as well as Dune Capital Management and Blackacre Institutional Capital Management, the real-estate arm of Cerberus Capital Management. Fortress didn't respond to a request for comment. The other lenders declined to comment.

 

Unless sales of the condo and hotel units restart despite the worst housing market in generations, and quickly generate $400 million in new sales, it will be difficult for the project to pay off the mezzanine loan, which comes due in May 2009.

Share this post


Link to post
Share on other sites
Trump Files Suit Against Lenders

Developer Seeks to Extend $640 Million Loan on a Chicago Skyscraper

 

P1130566.JPG

 

Wsj.com

By ALEX FRANGOS

 

 

The tower will be the second-tallest building in the U.S. behind Chicago's Sears Tower

 

 

Really? :confused:

Share this post


Link to post
Share on other sites

^ yes, with its spire the total height is 415 m ( = old World Trade Center Tower 2).

 

Sinon c'est un immeuble de 360 m (un peu plus haut que John Hancock) si on s'arrête au toit.

Share this post


Link to post
Share on other sites

Talk about giant egos!!!!

 

trump-sign-061314-1.jpg

 

http://www.nbcchicago.com/blogs/ward-room/Jon-Stewart-Weighs-in-on-Emanuel-Trump-Sign-Fight-263658081.html

 

Wading into the controversy over Donald Trump's new sign in Chicago, Jon Stewart joked the city should have known what it was getting into.

 

"I gotta say Chicago, I think this is on you," the host of "The Daily Show" said Tuesday night. "Did you not think Donald Trump was going to put his name on the building you let him build? It's what he does. Have you been to New York City? Or as you think it would be called from the buildings, New Trump City?"

 

"He put up a string of apartment buildings that literally block the sun from the entire Upper West Side of Manhattan," Stewart said.

 

The 20-foot illuminated letters spelling TRUMP on the side of Trump International Hotel over the Chicago River prompted criticism from Mayor Rahm Emanuel, who called the sign "architecturally tasteless."

 

Source: http://www.nbcchicago.com/blogs/ward-room/Jon-Stewart-Weighs-in-on-Emanuel-Trump-Sign-Fight-263658081.html#ixzz3512xTr6o

Follow us: @nbcchicago on Twitter | nbcchicago on Facebook

Share this post


Link to post
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Restore formatting

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

Sign in to follow this  

  • Similar Content

    • By paulmtl
      Désolé je sais pas où  mettre cette discussion.  Test de sol cette après midi dans le même secteur Viger coin Saint-Dominique .

    • By nephersir7
      Projet locatif de 18 étages à côté de Concordia

      http://www.lobby.gouv.qc.ca/servicespublic/consultation/AfficherInscription.aspx?NumeroInscription=3teoJdC%2bIdl2362AMJKTRg%3d%3d#D107088
       
    • By UrbMtl
      Hotel Peel

       
       
    • By Furn25
      Je crois que ce projet en construction mérite un thread.
       
      Projet du massif de Charlevoix: trois chantiers en simultané
       
      Sylvain Desmeules, collaboration spéciale
      Le Soleil
       
      (Baie-Saint-Paul) Le projet du Massif risque de changer le visage touristique de Charlevoix. Les trois chantiers sont actuellement menés de front, et malgré les retards, les dépassements de coûts, les rumeurs entendues, le projet verra bel et bien le jour, comme ont pu le constater les médias hier, invités à une visite de chantier.
       
      On ne construit pas tout un ensemble récréotouristique d'une valeur 258 millions $ sans avoir un effet sur l'offre touristique. Le printemps prochain, le train touristique aura fait ses premiers voyages, l'hôtel accueilli ses premiers clients et la montagne de ski, ses premiers lugeurs. L'intérêt grandit, mais aussi la curiosité, puisque nombreux sont les futurs clients qui sont impatients de voir la couleur de ce mégaprojet. C'est sans compter les centaines d'emploi, autant pour la construction que pour les opérations après coup.
       
      Les 150 chambres seront réparties en cinq pavillons. Le bâtiment principal qui comprendra une salle multifonctionnelle de 500 invités et le restaurant, est en construction. Une passerelle le relie à la gare où, là encore, des chambres de type nomade logeront aux niveaux supérieurs.
       
      Centre de soins de santé avec spa, marché public, comptoir du terroir, restaurants, place publique, le tout doublé d'événements festifs, risquent de faire de l'hôtel un pôle d'attraction de Baie-Saint-Paul.
       
      On parle ici de chambres «minimalistes et sobres», avec un «confort supérieur». L'utilisation de bois et un environnement de champs et de boisés rappelleront le passé agricole de ce secteur. D'un côté, les clients s'abreuveront d'un paysage agricole avec en toile de fond le fleuve Saint-Laurent, de l'autre, ils seront attirés par le village de Baie-Saint-Paul, accessible à pied.
       
      L'hôtel ouvrira au printemps prochain.
       
      Piste de luge
       
      La construction d'une piste de luge de 7,5 kilomètres, «une première en Amérique du Nord», comme se plaît à le dire le directeur général de la station de ski, Pierre Raymond, risque d'être l'attraction de l'hiver.
       
      Les lugeurs (10 ans et plus) seront amenés par groupes de 15 au sommet du mont à Liguori, d'où ils s'élanceront, soit sur une luge traditionnelle autrichienne, soit sur une luge non traditionnelle, couchés sur le ventre. Les plus vites négocieront le parcours en 30 minutes. À mi-chemin, un refuge et une passerelle avec vue sur de superbes chutes permettront une courte pause.
       
      Ceux qui arriveront par le train touristique ou la navette ferroviaire (en 2012) pourront emprunter une télébenne qui les mènera directement de la gare le long du fleuve au pied des pentes de la montagne. La construction d'une spectaculaire passerelle de 100 mètres au-dessus de la rivière Grande-Pointe fera le lien avec le chalet de la base.
       
      Ce n'est pas pour cette année, mais le projet comprend aussi la construction d'hébergement en montagne, soit près de 400 unités incluant les fameuses «maisons signature», sorte d'expérience singulière axée sur la mer, le vent ou les grands espaces.
       
      Le train
       
      C'est connu, le train touristique fera son voyage inaugural le 9 septembre. Les voyageurs auront droit à une escapade de trois heures trente de 140 kilomètres longeant le littoral, du parc de la Chute-Montmorency à La Malbaie. Le chemin de fer a subi une cure de rajeunissement de 20 millions $ en 22 mois, avec notamment le remplacement de 22 kilomètres de rail et des interventions sur 25 ponts et 86 ponceaux.
       
      Les huit voitures pourront embarquer 528 passagers. Le Massif a garanti 27 départs à l'automne. Pour 249 $, les clients auront droit à un dîner trois services à l'aller et à un souper gastronomique quatre services au retour, incluant une escale de trois heures à La Malbaie.
       
      110 millions $ dépensés
       
      Le président-directeur général du Massif, Claude Choquette, est content de ce qu'il voit. Il assure que les échéanciers sont respectés.
       
      Actuellement, 110 des 258 millions $ prévus au projet ont été engagés, ce qui permet de déduire que plus de 40 % du projet est réalisé.
       
      Reste encore des demandes d'aide financière du gouvernement en suspens, résultats des ajustements liés au contexte parasismique de Charlevoix.
       
      «Le projet est toujours de 258 millions $. On a fait des demandes au gouvernement pour nous aider à certains niveaux, pour des coûts supplémentaires. C'est sous analyse actuellement», nous dit M. Choquette. Pour rendre les bâtiments conformes aux normes sismiques, il a fallu ajouter entre 7 et 8 millions $ au projet.
       
      Rappelons que l'hôtel est construit dans une zone à haut risque sismique. On voit, de l'hôtel, l'Hôpital de Baie-Saint-Paul, condamné à être détruit en raison de sa vulnérabilité à un fort séisme.
       

      http://www.lemassif.com/fr/accueil