Montréal doesn't seem so bad when you compare to the project management of the NYC Port Authority..WOW

 

http://www.nytimes.com/2014/12/03/nyregion/the-4-billion-train-station-at-the-world-trade-center.html?ref=nyregion&_r=2

 

How Cost of Train Station at World Trade Center Swelled to $4 Billion :ohmygod:

 

With its long steel wings poised sinuously above the National September 11 Memorial in Lower Manhattan, the World Trade Center Transportation Hub has finally assumed its full astonishing form, more than a decade after it was conceived.

 

Its colossal avian presence may yet guarantee the hub a place in the pantheon of civic design in New York. But it cannot escape another, more ignominious distinction as one of the most expensive and most delayed train stations ever built.

 

The price tag is approaching $4 billion, almost twice the estimate when plans were unveiled in 2004. Administrative costs alone — construction management, supervision, inspection, monitoring and documentation, among other items — exceed $655 million.

 

Even the Port Authority of New York and New Jersey, which is developing and building the hub, conceded that it would have made other choices had it known 10 years ago what it knows now.

 

“It looks like a bird carcass picked clean. Not the intended symbolism, I'm sure.”

 

“We would not today prioritize spending $3.7 billion on the transit hub over other significant infrastructure needs,” Patrick J. Foye, the authority’s executive director, said in October.

 

The current, temporary trade center station serves an average of 46,000 commuters riding PATH trains to and from New Jersey every weekday, only 10,000 more than use the unassuming 33rd Street PATH terminal in Midtown Manhattan. By contrast, 208,000 Metro-North Railroad commuters stream through Grand Central Terminal daily.

 

In fact, the hub, or at least its winged “Oculus” pavilion, could turn out to be more of a high-priced mall than a transportation nexus, attracting more shoppers than commuters. The company operating the mall, Westfield Corporation, promises in a promotional video that it will be “the most alluring retail landmark in the world.”

 

But whatever its ultimate renown, the hub has been a money-chewing project plagued by problems far beyond an exotic and expensive design by its exacting architect, Santiago Calatrava, according to an examination based on two dozen interviews and a review of hundreds of pages of documents. The soaring price tag has also been fueled by the demands of powerful politicians whose priorities outweighed worries about the bottom line, as well as the Port Authority’s questionable management and oversight of private contractors.

 

George E. Pataki, a Republican who was then the governor of New York, was considering a run for president and knew his reputation would be burnished by a train terminal he said would claim a “rightful place among New York City’s most inspiring architectural icons.” He likened the transportation hub to Grand Central and promised — unrealistically — that it would be operating in 2009.

 

But the governor fully supported the Metropolitan Transportation Authority’s desire to keep the newly rebuilt No. 1 subway line running through the trade center site, instead of allowing the Port Authority to temporarily close part of the line and shave months and hundreds of millions of dollars off the hub’s construction. That, however, would have cut an important transit link and angered commuters from Staten Island, a Republican stronghold, who use the No. 1 line after getting off the ferry.

 

The authority was forced to build under, around and over the subway line, at a cost of at least $355 million.

Lien vers le commentaire
Partager sur d’autres sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Invité
Répondre à ce sujet…

×   Vous avez collé du contenu avec mise en forme.   Supprimer la mise en forme

  Seulement 75 émoticônes maximum sont autorisées.

×   Votre lien a été automatiquement intégré.   Afficher plutôt comme un lien

×   Votre contenu précédent a été rétabli.   Vider l’éditeur

×   You cannot paste images directly. Upload or insert images from URL.



×
×
  • Créer...